Concrete Sidewalk:Concrete pour scheduled for this morning at 7am until noon. Single lane traffic will be implemented over the slough during the pour then back to 2-way traffic for the afternoon. Please follow direction by traffic flaggers and pass with care....
Paving:Due to the rain, the paving crew is planning to start later this morning. If the weather clears, they will continue work on completing the paving in the Community Hall Parking Lot, then move to complete the Water Treatment Plant parking lot. The second lift of...
Paving: The paving crew will start on the Community Hall Parking Lot today. Heavy equipment will be present all day, the parking lot will be closed for the day and reopened once paving is completed. The paving crew is anticipated to work on the water treatment plant...
Sanitary Works: The Sanitary Works are COMPLETE and normal use of the sanitary system can resume. Thank you for your patience and cooperation. Paving: The paving crews are mobilizing to site and paving is expected to start at the Community Hall Parking Lot on Tuesday...
Road Construction Update & Sanitary Works OF NOTE: Kalum Road West is having concrete poured right now for the sidewalk. Watch for flaggers in this area. Houses on Gila Guaw Crescent, Spokeshute and West Kalum Road will be affected by sanitary works taking place...
Formwork for the concrete curb and gutter is being completed today. The concrete pour is scheduled for tomorrow, May 19th at 8am. During the concrete pour, the road along the concrete sidewalk will be reduced to 1 lane with flaggers directing traffic on either side....