Please see below construction update. Also note, the second lift of paving was completed on Kalum and Kwinitsa road on Saturday last weekend, but due to rain, the crew could not complete the patch work in the Band Office parking lot. The paving crews are back to work...
Quick Paving Update: The crew will attempt to complete the second lift along Kalum road today, June 3rd. Pending the weather this weekend, the crews will be completing the second lift of asphalt at the Hwy 16 and Kalum Road intersection by the Tempo Gas Station. This...
The Kitsumkalum Band office is currently moving contents of the basement offices to storage. As a West Kalum Road resident please be prepared for possible flooding of your home. Start moving the contents of your basement or lower level to higher levels of your home....
Quick update: the paving schedule has changed and the crew is setting up to complete the second lift over the slough (approx. Sta. 5+080 to Sta. 5+240) instead of the Cul-de-Sacs. Single traffic lanes are in place for this area during paving and the entrance towards...
Ama G̱anłaak, Paving: The paving crew will start the day by tying in the intersections along Kalum road. The crew is set up at Ecstall road to start, then will move to Gyiik Road intersection. Once these intersections are completed (approx. 2 or 3 hours this morning),...