Kalum Road: There will be a single lane open over the final section of road to be prepared and subbase placed with heavy equipment travelling in this section, traffic are to watch for flaggers and follow their direction. Compaction testing will also be occurring along...
Kalum Road: Crews are back to work on the subbase for Kalum Road and the same detour as last week will be in place. Traffic will be routed along the quarry road and over the berm to access Gyiik Road via Ecstall and Kwinitsa Road. As the crews progress the detour...
The road crew is progressing well along Kalum Road West and will likely reach the Gyiik road intersection by the end of the week. Flaggers remain on either end of the working zone and construction is accommodating driveways at the end of each day to ensure vehicles...
Please be advised that construction has started on Kwinitsa Road this morning. Heavy equipment will be working on this road with access only to local traffic through Gyiik Road. Flaggers are stationed to assist in directing traffic on either side of the working zone....
Tentative plan: Monday, March 14, 2022 Mobilization of equipment. Tuesday, March 15, 2022 Replace manhole in front of the Water Treatment Plant, and replacement of the sanitary sewer line between 3574 and 3530 West Kalum Road. This work is expected to take 12 days to...