The Kitsumkalum Band office is currently moving contents of the basement offices to storage. As a West Kalum Road resident please be prepared for possible flooding of your home. Start moving the contents of your basement or lower level to higher levels of your home....
Quick update: the paving schedule has changed and the crew is setting up to complete the second lift over the slough (approx. Sta. 5+080 to Sta. 5+240) instead of the Cul-de-Sacs. Single traffic lanes are in place for this area during paving and the entrance towards...
Ama G̱anłaak, Paving: The paving crew will start the day by tying in the intersections along Kalum road. The crew is set up at Ecstall road to start, then will move to Gyiik Road intersection. Once these intersections are completed (approx. 2 or 3 hours this morning),...
Hello Kitsumkalum Community, As of today, Kitsumkalum emergency management department has activated an Emergency Operation Center level 1 (EOC level 1) for Kitsumkalum community. Our emergency management team will be closely working with emergency management BC to...
Ama G̱anłaak, Paving:The paving crew plans to continue work on the second lift along West Kalum and Spokeshute Roads tomorrow. The crew will start work at the Highway 16 and Spokeshute Road intersection around 7am Wednesday morning to complete one lane. Crews will...