Scheduled to start work on Monday, June 12, 2023. Below is the proposed schedule for the well drilling activities planned around the water treatment plant for this week:

Monday, June 12
• Personnel On-Site: Associate Environmental
• Task(s): Site walk through at around 5:00 PM & install silt fence.

Tuesday, June 13
• Personnel On-Site: Kitsumkalum Public Works, Kitsumkalum Environmental Monitor, Kleanza Archaeological Monitor, Associated Environmental & Double D Drilling
• Task(s): Bird nest survey early morning & start drilling first well.

Wednesday, June 14
• Personnel On-Site: Associate Environmental & Double D Drilling
• Task(s): Finish drilling first well, develop well, and collect water samples.

Thursday, June 15
• Personnel On-Site: Kleanza Archaeological Monitor, Associated Environmental & Double D Drilling
• Task(s): Start drilling second well.

Friday, June 16
• Personnel On-Site: Kitsumkalum Environmental Monitor, Associated Environmental & Double D Drilling
• Task(s): Finish drilling second well, develop well, collect water samples,
site clean-up & demobilisation.

Please contact Kitsumkalum’s Public Works Manager, Richard Inkster (250-615-6911), if you have any
questions.