Road Construction Update & Sanitary Works OF NOTE: Kalum Road West is having concrete poured right now for the sidewalk. Watch for flaggers in this area. Houses on Gila Guaw Crescent, Spokeshute and West Kalum Road will be affected by sanitary works taking place...
Formwork for the concrete curb and gutter is being completed today. The concrete pour is scheduled for tomorrow, May 19th at 8am. During the concrete pour, the road along the concrete sidewalk will be reduced to 1 lane with flaggers directing traffic on either side....
Work on the concrete sidewalks is continuing this week. The barricades along this section on Kalum Road will be pulled out further into the road, but with enough room for 2-way traffic to be maintained. Please reduce speed and drive with care in this area over the...
There is no work scheduled for today. The Community Hall parking lot will be accessible for the event scheduled on Saturday, May 14. We ask those using the parking lot to drive safely and avoid rapid turns in the area which would cause the newly placed gravel to be...
CAUTION NOTICE The new school is under construction and the construction site is CLOSED TO THE PUBLIC. Please report any urgent safety concerns to CCM Construction at...
The contractor will be back on site starting tomorrow, Wednesday, May 11, and plan to complete the final placement and compaction of the 25mm IGB base course material at the Community Hall Parking Lot in preparation for paving starting next week. Once this area is...